Determining a schedule of values
Specialty Fabrics Review | July 2010
By Samuel J. Armijos, AIA
The best way to understand the cost of a fabric structure is to request a schedule of values (SOV) or a breakdown of the major costs.
Design (5-15%)
Design development to construction document. Percentage varies depending on design/build vs. plans and specification approach.
Engineering (5-15%)
Awning to dome stadium. All projects require a structural analysis. It depends on how many load cases are required.
Project management (5-15%)
Varies depending on the scope of the work. Some projects are membrane only while most are single-source complete structures.
Steel and fabrication (10-60%)
Large variable. Mast-supported structures vs. frame-supported structures.
Membrane and fabrication (10-60%)
Cost varies depending on the complexity of design.
Installation (10-30%)
Cost varies depending on labor rates and location.
Equipment (5-10%)
Cost varies depending on access and site location.
Shipping (1-5%)
Membrane is fabricated around the world. Shipping cost may include sea freight, air freight, dedicated trucks. Cost varies depending on gas prices and final destination.